O&G was contracted for the 107,000 GSF Windham Intermodal Transportation Center in downtown Willimantic, Connecticut. Despite challenging winter weather conditions, O&G self-performed all the site work and concrete foundation placement in preparation for the erection of the 343 prefabricated components of the structure. Working closely with the Windham Town Engineer, design team, and trade contractors, we successfully completed the project on schedule and close to $1,000,000 under budget.
- Town of Windham
Client
- General Contracting
Services
- N/A
Size
- $11.2M
Value
PROJECT Details

Architect
- Walker Consultants: Architect, VHB: Civil Engineer, GZA: Geotechnical Engineer, Walker: MEP/Structural Engineer