While the University of Saint Joseph recently celebrated the groundbreaking for its Pope Pius XII Library renovation, important work was already underway to keep the project moving and minimize disruption to the active campus.
As part of O&G’s scope, the team is constructing a large concrete retaining and screen wall to conceal a cooling tower adjacent to the entrance of the university’s new Welcome Center. The cooling tower and associated chiller serve the library, as well as two nearby academic buildings that are occupied year-round.
To accommodate the new addition, the cooling tower needed to be rotated 90 degrees, requiring a temporary cooling shutdown. With university events and classes scheduled, limiting downtime was critical.
Through the preconstruction process, O&G identified a solution. Preconstruction Manager Mark Sedensky, working closely with Superintendent Mike Sasso and the project team, coordinated with the structural engineer to use precast concrete footings instead of the originally designed cast-in-place footings.
The change reduced installation time by approximately 75 percent and gave the contractor setting the piers the flexibility to adjust them to the existing equipment stand layout.
The carefully coordinated five-day shutdown was completed on schedule. Thanks to O&G’s project team and trade partners, Mizzy Construction, Inc., Pro-Mech, Inc., C&H Electric, Inc., and General Welding, Inc., cooling was restored in time for scheduled university events and classes.
For O&G, the effort is a clear example of the value of preconstruction: identifying challenges early, collaborating with designers and trade partners, and developing practical solutions before issues become larger problems in the field.
At USJ, that planning helped support continuous campus operations while advancing the transformation of the Pope Pius XII Library and the university’s new Welcome Center.